Industry & Energy Techical Projects | 210 6619 590 | info@bienter.gr

Timetable of work: June-July 2014 

BIENTER SA undertook to provide services relating the implementation of the Technical and Economic assessment of improvement work already implemented or will be implemented in future, at the small hydro-electric power project SHPP THERMOREMA 2,9 MWe in Sperchiada, Fthiotida.
 -TURN KEY construction by BIENTER SA 
-Year of project 2003 

ACTIVITIES:
  • Position spreader pipe length 5.900m, material GRP, diameter F800-F900, pressure of 6 atm. up to 32 atm.
  • Improvement works to existing abstraction mainly in various construction and earthworks
  • Jobs which have already been implemented in existing abstraction and mainly in launching and re-build the project exammoti of reinforced concrete.
  • Work on the restoration and management of landslide damage to the pipeline flow of SHP THERMOREMA.
  • Construction work relating to construction of a new pipeline segment 1050m, Material GRP, F1100 diameter, pressure of 25 atm. to 32atm. to bypass the section of the pipeline suffered landslide.